- Asked by: Miles Briggs, MSP for Lothian, Scottish Conservative and Unionist Party
-
Date lodged: Monday, 20 February 2023
-
Current Status:
Answered by Elena Whitham on 1 March 2023
To ask the Scottish Government how many people have (a) received legal aid and (b) had an application for legal aid declined in each year since 1999.
Answer
Financial Year | Number of applications to SLAB | Grants of applications to SLAB | Total not granted* | Number of other** grants of legal aid |
1999-2000 | 88,000 | 74,000 | 14,000 | 361,000 |
2000-2001 | 90,000 | 76,000 | 14,000 | 370,000 |
2001-2002 | 97,000 | 82,000 | 15,000 | 371,000 |
2002-2003 | 99,000 | 87,000 | 12,000 | 362,000 |
2003-2004 | 101,000 | 88,000 | 13,000 | 353,000 |
2004-2005 | 103,000 | 90,000 | 13,000 | 339,000 |
2005-2006 | 103,000 | 90,000 | 13,000 | 322,000 |
2006-2007 | 106,000 | 93,000 | 13,000 | 316,000 |
2007-2008 | 99,000 | 86,000 | 13,000 | 275,000 |
2008-2009 | 82,000 | 71,000 | 11,000 | 242,000 |
2009-2010 | 83,000 | 71,000 | 12,000 | 221,000 |
2010-2011 | 80,000 | 64,000 | 17,000 | 208,000 |
2011-2012 | 91,000 | 79,000 | 12,000 | 183,000 |
2012-2013 | 85,000 | 71,000 | 14,000 | 175,000 |
2013-2014 | 92,000 | 78,000 | 14,000 | 168,000 |
2014-2015 | 90,000 | 74,000 | 16,000 | 156,000 |
2015-2016 | 89,000 | 72,000 | 17,000 | 150,000 |
2016-2017 | 83,000 | 71,000 | 11,000 | 147,000 |
2017-2018 | 77,000 | 67,000 | 11,000 | 147,000 |
2018-2019 | 73,000 | 64,000 | 9,000 | 138,000 |
2019-2020 | 75,000 | 67,000 | 8,000 | 135,000 |
2020-2021 | 65,000 | 59,000 | 6,000 | 104,000 |
2021-2022 | 72,000 | 63,000 | 9,000 | 103,000 |
Notes
Figures provided by Scottish Legal Aid Board. SLAB is unable to say how many individuals have been granted legal aid as it is possible for a person to have more than one grant of legal aid.
All figures are rounded to the nearest 1000 cases.
Due to rounding, some totals may not correspond with the subtraction of the separate figures.
*Not granted figures include cases refused and those where the application process was not completed.
**Other grants includes grants of legal assistance by solicitors and by the courts.
- Asked by: Jeremy Balfour, MSP for Lothian, Scottish Conservative and Unionist Party
-
Date lodged: Wednesday, 08 February 2023
-
Current Status:
Answered by Ben Macpherson on 1 March 2023
To ask the Scottish Government whether it will provide an update on the potential delays to the delivery of the Winter Heating Payment, and when the payments will reach those in need.
Answer
There has been no delay to making Winter Heating Payments. Payments started in February and will continue to be made automatically during March to support 400,000 eligible people.
While it was not possible to make payments earlier this year since the Department for Work and Pensions (DWP) were unable to provide the data required prior to 31 January, the Scottish Government is working with the DWP to review the feasibility of bringing forward payments in future years.
- Asked by: Miles Briggs, MSP for Lothian, Scottish Conservative and Unionist Party
-
Date lodged: Tuesday, 21 February 2023
-
Current Status:
Answered by Neil Gray on 1 March 2023
To ask the Scottish Government how many public libraries are currently at risk of closure.
Answer
Responsibility for public libraries sits with the relevant local authorities, and as such, this information is not held centrally by the Scottish Government. However, Scottish Government officials work closely with the Scottish Library and Information Council (SLIC) and the Convention of Scottish Local Authorities (COSLA) to ensure that Ministers are kept aware of relevant local issues as they arise. Information provided by the Scottish Libraries and Information Council showed that no Scottish Libraries have permanently closed in the last three reporting years.
- Asked by: Beatrice Wishart, MSP for Shetland Islands, Scottish Liberal Democrats
-
Date lodged: Tuesday, 21 February 2023
-
Current Status:
Answered by Mairi Gougeon on 1 March 2023
To ask the Scottish Government, regarding the avian flu virus, what actions are being taken to monitor (a) it, (b) how and where it is changing and (c) the population being affected, in light of reports of avian flu being detected in non-avian wild mammals.
Answer
In addition to statutory surveillance for Avian Influenza in poultry and wild birds, he Animal and Plant Health Agency (APHA) conducts surveillance in wild mammals at risk of being infected with the avian virus on behalf of the Scottish Government. In the event of a positive result, genetic analysis is performed by the APHA and the UK Health Security Agency.
In February 2023 genetic analysis carried out on historical samples from two positive Scottish seals, collected in 2021 and 2022, identified a genetic mutation associated with increased risk to mammals. As a single mutation, this does not indicate that this virus is becoming fully adapted to a mammalian host, nor will trigger mammal to mammal transmission.
- Asked by: Jamie Halcro Johnston, MSP for Highlands and Islands, Scottish Conservative and Unionist Party
-
Date lodged: Monday, 30 January 2023
-
Current Status:
Answered by Jenny Gilruth on 28 February 2023
To ask the Scottish Government what the current estimated total cost, including design, contract management, construction, legal, and administrative costs, is for the upgrading of the ferry terminal at Uig to allow its use by Hull 802, and what percentage of the total cost will be funded by (a) it and (b) other bodies.
Answer
The works at each of the ports as part of the Skye Triangle Infrastructure Programme (Tarbert, Lochmaddy & Uig) are aimed at replacing life expired infrastructure, improving resilience and increasing the range of vessels that can use the ports. The Uig project is estimated to cost £64million. Our response to the Freedom of Information request: 2022/00297832 published in July 2022 outlined that we have offered a capital funding contribution of up to £38million with the remaining contribution to be met by the Highland Council as statutory harbour authority.
- Asked by: Jamie Halcro Johnston, MSP for Highlands and Islands, Scottish Conservative and Unionist Party
-
Date lodged: Monday, 30 January 2023
-
Current Status:
Answered by Jenny Gilruth on 28 February 2023
To ask the Scottish Government, before an order was placed for Hull 802, whether an alternative option of ordering two smaller vessels to serve on the Uig to Lochmaddy and Uig to Tarbert ferry routes was considered, and, if it was the case, for what reason any such alternative option was rejected, and, if it was not the case, for what reason such an alternative option was not considered.
Answer
The proposal for the procurement of what became vessels 801 and 802 was set out in the Vessel Replacement and Deployment Plan (VRDP) Annual Report 2014 vrdp-annual-report-2014.pdf (transport.gov.scot)
The recently published Ferries Plan 2013-2022 had concluded that the level of services then in place on the Uig-Tarbert/Lochmaddy routes met identified community needs. Vessel 802 was earmarked for initial deployment to those services, to bring additional vehicle deck capacity; noting that the deployment plan would be reviewed prior to delivery.
- Asked by: Jamie Halcro Johnston, MSP for Highlands and Islands, Scottish Conservative and Unionist Party
-
Date lodged: Monday, 30 January 2023
-
Current Status:
Answered by Jenny Gilruth on 28 February 2023
To ask the Scottish Government what the current estimated total cost, including design, contract management, construction, legal, and administrative costs, is for the upgrading of the ferry terminal at Tarbert to allow its use by Hull 802, and what percentage of the total cost will be funded by (a) it and (b) other bodies.
Answer
The works at each of the ports as part of the Skye Triangle Infrastructure programme (Tarbert, Lochmaddy & Uig) are aimed at replacing life expired infrastructure, improving resilience and increasing the range of vessels that can use the ports. The Tarbert (Harris) project is estimated to cost £23million. Our response to the Freedom of Information Request 2022-00297832 published in July 2022 outlined that we have offered a capital funding contribution of up to £19.599million with the remaining contribution to be met by Caledonian Maritime Assets Ltd (CMAL) as statutory harbour authority.
- Asked by: Jamie Halcro Johnston, MSP for Highlands and Islands, Scottish Conservative and Unionist Party
-
Date lodged: Monday, 30 January 2023
-
Current Status:
Answered by Jenny Gilruth on 28 February 2023
To ask the Scottish Government what the current estimated total cost, including design, contract management, construction, legal, and administrative costs, is for the upgrading of the ferry terminal at Lochmaddy to allow its use by Hull 802, and what percentage of the total cost will be funded by (a) it and (b) other bodies.
Answer
The works at each of the ports as part of the Skye Triangle Infrastructure programme (Tarbert, Lochmaddy & Uig) are aimed at replacing life expired infrastructure, improving resilience and increasing the range of vessels that can use the ports. The Lochmaddy project is estimated to cost £21million. Our response to the Freedom of Information Request 2022-00297832 published in July 2022 outlined that we have offered a capital funding contribution of up to £15,747million with the remaining contribution to be met by the Comhairle nan Eilean Siar (CNES) as statutory harbour authority.
- Asked by: Neil Bibby, MSP for West Scotland, Scottish Labour
-
Date lodged: Monday, 30 January 2023
-
Current Status:
Answered by Jenny Gilruth on 28 February 2023
To ask the Scottish Government which local authorities have expressed interest in the Community Bus Fund.
Answer
No expressions of interest have been received by the Scottish Government as the Community Bus Fund has not launched. Officials have engaged with local authority representatives ATCO and CoSLA, who have indicated the general feedback from local authorities on the Community Bus Fund has been positive.
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Friday, 10 February 2023
-
Current Status:
Answered by Humza Yousaf on 28 February 2023
To ask the Scottish Government how many of the 300 additional interim care home beds, identified in January 2023, have since been used, broken down by NHS board.
Answer
Data around the number of people taking up interim care placements procured using the additional funding offer announced in January 2023 is published weekly on a Thursday at Interim care placement uptake - gov.scot (www.gov.scot) .
The data is currently not available broken down by NHS board.