- Asked by: Paul McLennan, MSP for East Lothian, Scottish National Party
-
Date lodged: Wednesday, 10 August 2022
-
Current Status:
Answered by Humza Yousaf on 6 September 2022
To ask the Scottish Government what plans it has to prepare a national framework for social prescribing, to facilitate a
consistent, effective and high-quality approach.
Answer
The Scottish Government is giving consideration to how best to ensure a consistent, effective and high quality approach to social prescribing and meets the Scottish Social Prescribing Network regularly to inform its plans.
- Asked by: Maurice Golden, MSP for North East Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Thursday, 11 August 2022
-
Current Status:
Answered by Lorna Slater on 6 September 2022
To ask the Scottish Government what its position is on whether Zero Waste Scotland would be able to provide independent
advice to the Scottish Government on the circular economy and other matters in
the event that it would also be in receipt of private sector funding.
Answer
Zero Waste Scotland (ZWS) is an independent not-for-profit company, which is able to locate, apply for and accept funding from a range of sources. As an evidence-led organisation, any expertise and/or advice ZWS provide to Scottish Government would be based on balanced outputs from research by sector specific policy experts.
ZWS is a key delivery partner for the Scottish Government in relation to circular economy policy and it would be for Scottish Government to decide on whether to use the organisations advice in development of policies.
- Asked by: Liam Kerr, MSP for North East Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Wednesday, 10 August 2022
-
Current Status:
Answered by Jenny Gilruth on 6 September 2022
To ask the Scottish Government, further to the answers to questions S6W-08649, S6W-09452 and S6W-09553 by Jenny Gilruth on 23 June and 28 July 2022, whether it can provide a breakdown of the figures provided in response to each of three questions for the North East region.
Answer
ScotRail does not record passenger complaints data by region, but by rail route. The following below table shows ScotRail’s complaints data for routes which serve the North East region.
Complaint Type | April | May | June |
1st Class | 14 | 21 | 28 |
Assisted Travel | 1 | 0 | 0 |
Capacity | 8 | 17 | 26 |
Contact Centre | 0 | 0 | 1 |
Customer Provisions | 1 | 6 | 0 |
Cycles | 1 | 1 | 1 |
Environment | 6 | 3 | 2 |
Policy And Product | 5 | 2 | 6 |
Staff | 5 | 3 | 3 |
Timetable | 0 | 5 | 2 |
Train Service Performance | 1 | 20 | 19 |
TOTAL | 42 | 78 | 88 |
ScotRail has confirmed that the routes detailed below were included in this data. The member should note that the data reflects complaints which may have occurred at any point on the route:
- Aberdeen-Edinburgh
- Aberdeen-Glasgow
- Aberdeen-Inverness
- Dundee-Glasgow
- Edinburgh-Arbroath
- Asked by: Pam Duncan-Glancy, MSP for Glasgow, Scottish Labour
-
Date lodged: Wednesday, 10 August 2022
-
Current Status:
Answered by Clare Haughey on 6 September 2022
To ask the Scottish Government whether it will involve those with lived experience of care in its work to improve Scotland's care
system.
Answer
The Scottish Government remains committed to Keeping The Promise by 2030, working in partnership with Local Authorities, The Promise Scotland, third sector, health boards and importantly the care community.
On 30 March 2022 the Scottish Government published the Keeping The Promise Implementation Plan , setting out how it will Keep The Promise by 2030. The Plan contains over 80 actions which span over a range of areas including education, health, justice and child poverty.
The Plan sets out how we will work with care experienced people in our design, delivery and evaluation of Keeping The Promise. We will continue work with stakeholders and care experienced people on our journey to Keeping The Promise by 2030.
- Asked by: Mark Griffin, MSP for Central Scotland, Scottish Labour
-
Date lodged: Friday, 05 August 2022
-
Current Status:
Answered by Shona Robison on 6 September 2022
To ask the Scottish Government, further to the answer to question S6W-09248 by Shona Robison on 20 July 2022, whether it will prioritise the assessment of the 29 buildings in the event of a limited supply of surveyors and fire engineer contractors, and if so, what the process will be for carrying out any such prioritisation.
Answer
We are aware there may be constraints in the market place and we are working closely with a number of Scottish firms and with industry bodies and forums to monitor market availability, therefore we are able to prioritise Single Building Assessments.
- Asked by: Mark Griffin, MSP for Central Scotland, Scottish Labour
-
Date lodged: Friday, 05 August 2022
-
Current Status:
Answered by Shona Robison on 6 September 2022
To ask the Scottish Government, further to the answer to S6W-09248 by Shona Robison on 20 July 2022, how many buildings (a) have provided consent and details (i) by and (ii) on or since 20 July 2022 and (b) it requires to provide consent and detail before it will move to the contracting process; what the estimated timescales are for the contracting process; and, when contracting, what it plans to propose as a lead time for surveyors and fire engineers to be on site.
Answer
We have confirmed consent from 26 buildings. We have consent in principle from the homeowners from 29 additional buildings since we invited new buildings into the programme in May 2022. The timescale for the contracting process follows the standard Scottish Government procurement rules. We are aware of the supply chain constraints in this field, which is why are working closely with Royal Institution of Chartered Surveyors and the Institute of Fire Engineers to ensure an appropriate stream of qualified assessors. Time scales for the completion of Single Building Assessments are driven by the complexity of the building and are agreed as part of the normal contracting process.
- Asked by: Mark Griffin, MSP for Central Scotland, Scottish Labour
-
Date lodged: Friday, 05 August 2022
-
Current Status:
Answered by Shona Robison on 6 September 2022
To ask the Scottish Government, further to the answer to question S6W-09248 by Shona Robison on 20 July 2022, what pre-contracting activity it has undertaken to establish (a) how many contractors will be required to deliver assessments for all 29 buildings, (b) the (i) availability and (ii) capacity of surveyors and fire engineers to carry out the contract, and, in the event that any such pre-contracting assessments have identified an insufficient supply of contractors, what it anticipates the likely training needs will be to meet any identified requirements.
Answer
Every building must gain the consent of homeowners in order to begin the contract process. Every building will require a qualified Fire Assessor to spend typically a number of weeks on and off-site to gather sufficient data and evidence to conduct a competent Single Building Assessment.
We are aware of the supply chain constraints in this field which is why we are working closely with Royal Institution of Chartered Surveyors and the Institute of Fire Engineers to ensure an appropriate stream of qualified assessors.
- Asked by: Mark Griffin, MSP for Central Scotland, Scottish Labour
-
Date lodged: Friday, 05 August 2022
-
Current Status:
Answered by Shona Robison on 6 September 2022
To ask the Scottish Government, further to the answers to questions S6W-09248 and S6W-09249 by Shona Robison on 20 July 2022,
how many of the 15 buildings using its grant-based approach (a) have (i) been approached
to take up and (ii) requested directly commissioned assessments, (b) successfully
procured their own surveyors and fire engineers and (c) have an assessment
underway.
Answer
All the 15 buildings using the grant based approach have been issued grant letters and had initial payments to allow contracts to be placed. All have fire engineers and surveyors working on assessments.
- Asked by: Mark Griffin, MSP for Central Scotland, Scottish Labour
-
Date lodged: Friday, 05 August 2022
-
Current Status:
Answered by Shona Robison on 6 September 2022
To ask the Scottish Government, further to the answer to question S6W-09252 by Shona Robison on 21 July 22, what the expenditure has been on the (a) Cladding Remediation Unit and (b) Single Building Assessment in each year since 2017, broken down by type of spending.
Answer
The Cladding Remediation Unit was set up in June 2021 in the Local Government and Communities Directorate. The expenditure on staff whose primary role is to support the programme is:
a)
Core Scottish Government: 2021 - £241,280.00
Core Scottish Government: 2022 (until July) - £113,635.44
Interim contractors 2021 - £52,938.90
Interim contractors 2022 (until July) - £105,369.00
b) Since the start of the Single Building Assessment programme in June 2021 we have grant funded £432,613.63 to support 12 buildings who are currently undergoing assessment. We have a further £510,553 in committed spend to finish these buildings assessments and support 3 additional buildings in starting their assessments through the grant funding model. We have an additional 29 buildings where we will use procurement functions to hire fire engineers and access contractors to begin assessments.
- Asked by: Mark Griffin, MSP for Central Scotland, Scottish Labour
-
Date lodged: Friday, 05 August 2022
-
Current Status:
Answered by Shona Robison on 6 September 2022
To ask the Scottish Government how the single building assessment is designed to take account of any risk of electric vehicle
fires, whether any specific assessment protocols are included in the assessment
to respond to any such risks and, if this is the case, whether it will provide
the details of any such protocols.
Answer
A Single Building Assessment will deliver a full assessment of fire risks on a building by building basis to highlight any issues related to fire safety including, but not limited to underground car parks and charging points.