- Asked by: Liam Kerr, MSP for North East Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Tuesday, 13 August 2019
-
Current Status:
Answered by Joe FitzPatrick on 4 September 2019
To ask the Scottish Government how many colposcopes have been installed since March 2017, and how many there will be by April 2020, broken down by NHS board.
Answer
This information is not held centrally by the Scottish Government. Information regarding clinical equipment should be directed to individual NHS Boards.
- Asked by: Liam Kerr, MSP for North East Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Wednesday, 14 August 2019
-
Current Status:
Answered by Michael Matheson on 2 September 2019
To ask the Scottish Government what discussions it has had with members of the public regarding improving rail connectivity in the North East Scotland region.
Answer
Transport Scotland meets regularly with North-East of Scotland Transport Partnership (NESTRANS) who represent the views of the local communities, local authorities and other key regional stakeholders.
In the first instance, promoters of new schemes should discuss their proposals with the relevant Regional Transport Partnership who consider the proposal and determine whether it fits with regional transport priorities.
NESTRANS were successful in the latest round of the Local Rail Development Fund (LRDF) and will be taking forward an appraisal in respect of cross-Aberdeen rail travel which includes consideration of new stations South of Aberdeen.
- Asked by: Liam Kerr, MSP for North East Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Wednesday, 14 August 2019
-
Current Status:
Answered by Michael Matheson on 2 September 2019
To ask the Scottish Government what research it has undertaken on the feasibility of opening a new railway station at Cove.
Answer
This Government is committed to improving rail connectivity, reliability and journey times throughout Scotland. However, any transport project which requires Government funding, must be supported by a transport appraisal to ensure that the solution is arrived at impartially, based on evidence and is objective rather than solution led. The Scottish Government’s £2 million Local Rail Development Fund can help with the cost of these appraisals and NESTRANS has recently secured £80,000 to carry out a multi-modal transport appraisal to look at opportunities to improve connectivity across Aberdeen.
- Asked by: Liam Kerr, MSP for North East Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Wednesday, 14 August 2019
-
Current Status:
Answered by Michael Matheson on 2 September 2019
To ask the Scottish Government whether it will provide an update on progress on upgrading Montrose railway station, and when upgrades to the station will be completed.
Answer
The procurement process for Montrose is now complete, and the formal papers are due for submission for funding agreement with Transport Scotland week beginning 26 August.
Works are due to commence in the Autumn, with a 12 week delivery programme leading to completion of the works by early 2020.
- Asked by: Liam Kerr, MSP for North East Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Wednesday, 14 August 2019
-
Current Status:
Answered by Michael Matheson on 2 September 2019
To ask the Scottish Government what discussions it has had with the local community regarding a new railway station at Cove.
Answer
Transport Scotland meets regularly with North-East of Scotland Transport Partnership (NESTRANS) who represent the views of the local communities, local authorities and other key regional stakeholders.
In the first instance, promoters of new schemes should discuss their proposals with the relevant Regional Transport Partnership who consider the proposal and determine whether it fits with regional transport priorities.
NESTRANS were successful in the latest round of the Local Rail Development Fund (LRDF) and will be taking forward an appraisal in respect of cross-Aberdeen rail travel which includes consideration of new stations South of Aberdeen, including Cove.
- Asked by: Liam Kerr, MSP for North East Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Tuesday, 13 August 2019
-
Current Status:
Answered by Michael Matheson on 2 September 2019
To ask the Scottish Government how much it will cost to carry out each of the snagging works on the AWPR/Balmedie to Tipperty Project, also plotted against the particular head or type of snagging identified.
Answer
Due to the nature of the Design, Build, Finance and Operate (DBFO) contract the cost of snagging works cannot be disaggregated from the construction cost of the project. All snagging costs will be borne by the AWPR/Balmedie to Tipperty contractor.
- Asked by: Liam Kerr, MSP for North East Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Wednesday, 14 August 2019
-
Current Status:
Answered by Michael Matheson on 2 September 2019
To ask the Scottish Government what consideration it has given to the feasibility of opening new railway stations in the North East Scotland region.
Answer
I refer the member to the answer to question S5W-24772 on 2 September 2019. All answers to written parliamentary questions are available on the Parliament’s website, the search facility for which can be found at http://www.parliament.scot/parliamentarybusiness/28877.aspx .
- Asked by: Liam Kerr, MSP for North East Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Wednesday, 14 August 2019
-
Current Status:
Answered by Michael Matheson on 2 September 2019
To ask the Scottish Government what plans it has to open new railway stations in the North East Scotland region.
Answer
The Scottish Government and partners are committed to delivering new railway stations at Kintore and Dalcross. In addition, NESTRANS has recently been successful in securing a share of the Scottish Government’s £2 million Local Rail Development Fund. This funding will allow NESTRANS to carry out a multi-modal transport appraisal to look at opportunities to improve connectivity across Aberdeen.
- Asked by: Liam Kerr, MSP for North East Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Tuesday, 13 August 2019
-
Current Status:
Answered by Jeane Freeman on 29 August 2019
To ask the Scottish Government when it will bring forward legislation to improve forensic medical services for victims of rape and sexual assault.
Answer
I refer the Member to the answer to question S5W-24987 on 29 August 2019. All answers to written parliamentary questions are available on the Parliament's website, the search facility for which can be found at: http://www.parliament.scot/parliamentarybusiness/28877.aspx
- Asked by: Liam Kerr, MSP for North East Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Tuesday, 13 August 2019
-
Current Status:
Answered by Michael Russell on 28 August 2019
To ask the Scottish Government what advice it has (a) sought and (b) received regarding the level of expansion of prisoner voting required to comply with the European Convention on Human Rights.
Answer
The Scottish Ministerial Code states that Ministers must not ordinarily divulge either the source or content of legal advice. Legal advice is confidential and it is a very long established convention that legal advice provided to the Scottish Government is not published, and that the Government does not disclose the source of advice.
I look forward to discussing my reasoning on prisoner voting at Committee and when the Parliament debates the Scottish Elections (Franchise and Representation) Bill.