- Asked by: Liam McArthur, MSP for Orkney, Scottish Liberal Democrats
-
Date lodged: Monday, 07 September 2009
-
Current Status:
Answered by Jim Mather on 18 September 2009
To ask the Scottish Executive whether it considers it good practice to consider a planning application for a coal-fired power station before it has produced its thermal generation guidance.
Answer
Under section 36 of the Electricity Act 1989, Scottish ministers are obliged to accept and consider all thermal power station applications in excess of 50 megawatts of generating capacity. Each application is subject to statutory consultation with the determination taking into account all material issues, including the thermal guidance applicable at the time the decision is made.
- Asked by: Liam McArthur, MSP for Orkney, Scottish Liberal Democrats
-
Date lodged: Monday, 07 September 2009
-
Current Status:
Answered by Jim Mather on 18 September 2009
To ask the Scottish Executive, given that it has yet to produce its thermal generation guidance, on what basis it will consider the planning application for the Hunterston power plant.
Answer
All thermal power station applications over 50 megawatts in generating capacity will be considered by Scottish ministers under section 36 of the Electricity Act 1989. Following a request from Ayrshire Power Limited, Scottish Ministers provided a scoping opinion on 20 March 2009 on the Hunterston project, which included a wide range of consultee advice on the outline design. The developer is currently working in partnership with stakeholders to develop an application which addresses the relevant planning, community and legislative issues, and we have recommended to the developer that they take into account in any application our draft guidance and the answer to question S3W-
24912 on 17 June 2009.
All answers to written parliamentary questions are available on the Parliament''s website, the search facility for which can be found at http://www.scottish.parliament.uk/Apps2/Business/PQA/Default.aspx.
- Asked by: Liam McArthur, MSP for Orkney, Scottish Liberal Democrats
-
Date lodged: Monday, 07 September 2009
-
Current Status:
Answered by Jim Mather on 18 September 2009
To ask the Scottish Executive whether it considers it premature to consider a planning application for a development, for the basis of which it has not formulated policy.
Answer
Under section 36 of the Electricity Act 1989, the building of any new thermal power station in excess of 50 megawatts in generating capacity would require consent from Scottish ministers. The Scottish Government published draft thermal guidance in late 2008 for consultation. We await the completion of the UK Government consultation, before publishing our final thermal guidance in Scotland.
- Asked by: Liam McArthur, MSP for Orkney, Scottish Liberal Democrats
-
Date lodged: Monday, 07 September 2009
-
Current Status:
Answered by Jim Mather on 18 September 2009
To ask the Scottish Executive when it expects to produce its thermal generation guidance.
Answer
The Scottish Government will issue its final thermal guidance later this year following consideration of responses to our own consultation and the subsequent UK consultation which closed on 9 September 2009.
- Asked by: Liam McArthur, MSP for Orkney, Scottish Liberal Democrats
-
Date lodged: Monday, 07 September 2009
-
Current Status:
Answered by Jim Mather on 18 September 2009
To ask the Scottish Executive whether it aims for new coal-fired power stations in Scotland to demonstrate carbon capture and storage capacity greater than that required in England and Wales.
Answer
The Scottish Government aims to encourage early carbon capture and storage deployment in Scotland with the objective of decarbonisation of the electricity sector by 2030.
styl
- Asked by: Liam McArthur, MSP for Orkney, Scottish Liberal Democrats
-
Date lodged: Monday, 07 September 2009
-
Current Status:
Answered by Jim Mather on 18 September 2009
To ask the Scottish Executive how it will encourage new coal-fired power stations to operate carbon capture and storage from the outset or to be able to meet an equivalent emissions performance standard by other means.
Answer
The Scottish Government''s thermal guidance will set out policy on the development of CCS technology for both new and existing power plant. This guidance will be issued following consideration of responses to our consultation on this subject last year and the completion of the UK consultation process.
- Asked by: Liam McArthur, MSP for Orkney, Scottish Liberal Democrats
-
Date lodged: Monday, 07 September 2009
-
Current Status:
Answered by Jim Mather on 18 September 2009
To ask the Scottish Executive whether it considers it acceptable for new coal-fired power stations to have a defined carbon capture and storage capacity of no more than 400 megawatt (gross).
Answer
The Scottish Government will issue its final thermal guidance later this year following the completion of the UK consultation process. This thermal guidance will set out policy on the introduction of CCS levels to new and existing power plant, in terms of timing and capacity.
- Asked by: Liam McArthur, MSP for Orkney, Scottish Liberal Democrats
-
Date lodged: Monday, 07 September 2009
-
Current Status:
Answered by Jim Mather on 18 September 2009
To ask the Scottish Executive what definition it uses of a carbon capture-ready power station.
Answer
The Scottish Government considers that a carbon capture ready power station will demonstrate consideration of the following criteria:
demonstrate that there is sufficient space on or near the site to accommodate carbon capture equipment in the future;
undertake an assessment into the technical and economic feasibility of retrofitting carbon capture technology;
propose a suitable area of deep geological storage offshore for the storage of captured CO2;
undertake an assessment into the technical and economic feasibility of transporting the captured CO2 to their proposed storage area, and
if necessary, apply for and obtain Hazardous Substance Consent (HSC).
This position applies to all new gas, oil, biomass, waste-to-energy and also coal power station applications on or above 300MW. This approach is in line with that taken by the UK Government and reflects the wish for a broadly similar regulatory framework across the UK.
- Asked by: Liam McArthur, MSP for Orkney, Scottish Liberal Democrats
-
Date lodged: Monday, 07 September 2009
-
Current Status:
Answered by Jim Mather on 18 September 2009
To ask the Scottish Executive what consultation it plans to carry out on the development of carbon capture and storage.
Answer
The Scottish Government held a consultation on its draft thermal guidance, which included questions on Carbon Capture and Storage (CCS) and Carbon Capture Readiness (CCR), which closed earlier this year. Following the consultation, we have had on-going engagement with stakeholders on the development of CCS through workshops and meetings. We have decided to await the completion of the UK consultation process on clean coal before issuing our final thermal generation guidance. This will ensure that the regulatory framework in broad terms is similar across the UK as a whole, with the overall objective of encouraging CCS deployment and the objective of decarbonisation of the electricity sector by 2030. In the meantime, we have set out our position on CCR for all thermal stations above 300MW.
This was set out in an answer to question S3W-24912 on 17 June 2009. All answers to written parliamentary questions are available on the Parliament''s website, the search facility for which can be found at http://www.scottish.parliament.uk/Apps2/Business/PQA/Default.aspx.
- Asked by: Liam McArthur, MSP for Orkney, Scottish Liberal Democrats
-
Date lodged: Monday, 07 September 2009
-
Current Status:
Answered by Jim Mather on 18 September 2009
To ask the Scottish Executive when it was decided to include Hunterston power station in the second National Planning Framework and what consultation has been carried out on its inclusion.
Answer
A new clean coal power station and a transhipment hub at Hunterston were among the projects proposed by stakeholders as additional national developments in representations on the NPF Discussion Draft. These projects were assessed against the criteria for national developments announced in a statement to Parliament by the Cabinet Secretary for Finance and Sustainable Growth in September 2007 and subsequently included amongst the candidate national developments which were subject to a Supplementary Strategic Environmental Assessment, including consultation, in autumn 2008. The NPF has also been the subject of detailed consideration by three committees of the Scottish Parliament and a debate in Parliament on 5 March 2009, ensuring a high level of scrutiny of the spatial strategy and national developments. The National Planning Framework Participation Statement available on the Scottish Government''s website details the full extent of consultation during the preparation of NPF2.