- Asked by: Patrick Harvie, MSP for Glasgow, Scottish Green Party
-
Date lodged: Thursday, 03 March 2011
-
Current Status:
Answered by Keith Brown on 16 March 2011
To ask the Scottish Executive what contingency liability there is for third parties affected by possible damage to the BP Forties pipeline system during construction of the Forth Replacement Crossing, for example as a result of evacuation and clean-up costs.
Answer
A contingent liability exists in connection with the proposed construction of the Forth Crossing where it impacts on the existing BP Fortes oil pipeline. The contingent liability is required to cover the remote possibility that the pipeline could be damaged as a result of the construction of the new bridge. This is a potential liability to the contract not a cost, and as such does not increase the estimated cost of the project.
- Asked by: Patrick Harvie, MSP for Glasgow, Scottish Green Party
-
Date lodged: Thursday, 03 March 2011
-
Current Status:
Answered by Keith Brown on 16 March 2011
To ask the Scottish Executive whether there are insurance policies or contingency liabilities in place for local residents and businesses for any damage incurred to them during construction of the Forth Replacement Crossing.
Answer
Insurance will be taken out to cover damage to third parties as a result of the construction of the Forth Replacement Crossing. There are no contingent liabilities in respect of those third parties.
- Asked by: Patrick Harvie, MSP for Glasgow, Scottish Green Party
-
Date lodged: Thursday, 03 March 2011
-
Current Status:
Answered by Keith Brown on 16 March 2011
To ask the Scottish Executive whether provision has been made for any damage to the BP Forties pipeline system after the Forth Replacement Crossing is completed and, if so, how this has been calculated and costed.
Answer
The issue has been discussed in confidence by the finance committee.
- Asked by: Patrick Harvie, MSP for Glasgow, Scottish Green Party
-
Date lodged: Tuesday, 08 March 2011
-
Current Status:
Answered by Jim Mather on 14 March 2011
To ask the Scottish Executive whether it will reconsider the consultation process on Forth Energy’s proposals for a biomass power station at Dundee given that many objections have not been acknowledged due to an invalid email address.
Answer
A decision was taken within the Energy Consents and Deployment Unit (ECDU) at the beginning of October 2010 to cease acknowledging representations in writing, due to the excessive costs involved. This meant that members of the public who submitted representations between the middle and end of September 2010, to the address energyconsents@scotland.gsi.gov.uk, or in writing, did not receive an acknowledgment.
The address energyconsents@scotland.gsi.gov.uk is not invalid, members of the public were asked to direct representations to the dedicated email address dundeebiomass@scotland.gsi.gov.uk to allow easier collation of these responses and to ensure they received the automatic acknowledgement. All representations received to either address have now been collated and logged.
There is no requirement under legislation to acknowledge, either in writing or electronically, representations received.
- Asked by: Patrick Harvie, MSP for Glasgow, Scottish Green Party
-
Date lodged: Tuesday, 08 March 2011
-
Current Status:
Answered by Jim Mather on 14 March 2011
To ask the Scottish Executive how many objection letters its Energy Consents Unit has received in relation to Forth Energy’s proposals for a biomass power station at Dundee and, of those, how many have been published on the relevant website.
Answer
To date, the Energy Consents and Deployment Unit (ECDU) have received 36 consultation responses from a variety of organisations with an interest in the development. These responses are all available on the Scottish Government website. The ECDU have also received 3,292 representations from members of the public. These are not published on the Scottish Government website to protect the identities of individuals.
- Asked by: Patrick Harvie, MSP for Glasgow, Scottish Green Party
-
Date lodged: Tuesday, 08 March 2011
-
Current Status:
Answered by Jim Mather on 14 March 2011
To ask the Scottish Executive for what reason an invalid email address was given on the Energy Consents Unit website for objections to be made to Forth Energy’s proposals for a biomass power station at Dundee and what steps it took to rectify this problem.
Answer
Press notices were placed in the Scotsman on 17 August 2010 and in the Dundee Courier and Edinburgh Gazette on 17 August 2010 and 24 August 2010 advising members of the public of the submission of the application. These notices advised members of the public to submit representations to energyconsents@scotland.gsi.gov.uk, which is the enquiries email address for the Energy Consents and Deployment Unit (ECDU). The second press notices for this development were placed in
The Scotsman on 9 November 2010 and in
The Courier and
Edinburgh Gazette on 9 November 2010 and 16 November 2010. These notices advised members of the public to submit representations to the dedicated Dundee Biomass email address dundeebiomass@scotland.gsi.gov.uk, which had been implemented to deal with the level of representations being received. The biomass section of the ECDU website quoted the dedicated email address as the point of contact during the consultation. The ECDU enquiries email address is quoted elsewhere on the website as general point of contact, hence no amendment or correction was required.
All representations received to either email addresses have been collated and logged.
- Asked by: Patrick Harvie, MSP for Glasgow, Scottish Green Party
-
Date lodged: Tuesday, 08 March 2011
-
Current Status:
Answered by Jim Mather on 14 March 2011
To ask the Scottish Executive whether it has acknowledged receipt of every objection letter that its Energy Consents Unit has received in relation to Forth Energy’s proposals for a biomass power station at Dundee.
Answer
There is no requirement under legislation to acknowledge, either in writing or electronically, representations received.
Due to the excessive cost, both in postage and in staff time, it is no longer the policy of the Energy Consents and Deployment Unit (ECDU) to respond in writing to representations received. Should the representation have been submitted by email, to the email address stated in the press notices, dundeebiomass@scotland.gsi.gov.uk, the author will receive an automatic acknowledgement. All representations received are collated and logged and form part of the final determination process for the application.
- Asked by: Patrick Harvie, MSP for Glasgow, Scottish Green Party
-
Date lodged: Thursday, 03 March 2011
-
Current Status:
Answered by Keith Brown on 14 March 2011
To ask the Scottish Executive what the actual cost to BP will be if the Forties pipeline system is damaged during construction of the Forth Replacement Crossing.
Answer
Financial information relating to those costs is commercially confidential and cannot be released. In any event, the actual costs cannot be determined in the abstract and will depend on the particular facts and circumstances.
- Asked by: Patrick Harvie, MSP for Glasgow, Scottish Green Party
-
Date lodged: Thursday, 03 March 2011
-
Current Status:
Answered by Keith Brown on 14 March 2011
To ask the Scottish Executive whether, in relation to the BP Forties pipeline system, Transport Scotland investigated whether it would be safer to move the Southern Approach Road to link directly from the new Forth Bridge on the west side of Dundas Castle to the M9 at Winchburgh and, if so, for what reason the report of that investigation was not made available as part of the environmental statement for the Forth Crossing Act 2011.
Answer
During 2008, Transport Scotland considered a number of alternative options for the southern connecting roads. An assessment of the options and the reasoning for their rejection is provided in the DMRB Stage 2 Corridor Report. The location of the BP pipeline was considered in this assessment. This is outwith the remit of the Environmental Statement.
- Asked by: Patrick Harvie, MSP for Glasgow, Scottish Green Party
-
Date lodged: Thursday, 03 March 2011
-
Current Status:
Answered by Keith Brown on 14 March 2011
To ask the Scottish Executive for what reason the contingency liability for BP has been capped at £100 million if the Forties pipeline system is damaged during the construction of the Forth Replacement Crossing.
Answer
The sum is typical of these types of arrangements in the Oil and Gas industry and was arrived at following negotiation with BP. The number represents the maximum potential liability under the Agreement and BP will bear any losses which exceed that amount.