The Official Report is a written record of public meetings of the Parliament and committees.
All Official Reports of meetings in the Debating Chamber of the Scottish Parliament.
All Official Reports of public meetings of committees.
Displaying 2151 contributions
Public Audit Committee
Meeting date: 16 June 2022
Colin Beattie
Yes, I mentioned the figure of £128.25 million.
FMEL accepted £45 million from the Scottish Government, but it said that it did not want the loans.
Public Audit Committee
Meeting date: 16 June 2022
Colin Beattie
Mr McColl, my main interest here is obviously in following the public pound. A lot of public money has been invested and I am keen to understand how it has been dealt with. At the point of nationalisation, the vessels were largely incomplete.
Public Audit Committee
Meeting date: 16 June 2022
Colin Beattie
I want to come back in on a couple of points that you touched on earlier. First, I have managed to dig out the cost of purchasing FMEL’s assets. I realise that there are all sorts of offset figures involved, so this is a crude figure, but it is £7.5 million. That was the valuation put on all the assets in the yard, which is very far short of the money that went in there.
Secondly, the milestone payments were £83.25 million. In fact, £82.5 million was for milestone payments, but £0.75 million was for contract variations. That seems a very small figure, after listening to what you have been saying—
Public Audit Committee
Meeting date: 16 June 2022
Colin Beattie
How can the committee identify those variations and understand the costs against them?
Public Audit Committee
Meeting date: 16 June 2022
Colin Beattie
What would your estimated value be?
Public Audit Committee
Meeting date: 16 June 2022
Colin Beattie
You are saying that the money was absorbed by changes and so on to the specifications. Is there any document that lays that out and puts cost against that?
Public Audit Committee
Meeting date: 16 June 2022
Colin Beattie
Why did FMEL never pursue its claim in court?
Public Audit Committee
Meeting date: 16 June 2022
Colin Beattie
So you are saying that the Government has this information.
Public Audit Committee
Meeting date: 16 June 2022
Colin Beattie
Certain statements in the RECC report seem to raise a question. For example, in paragraph 157, the report states:
“the profile of milestone payments may have resulted in the contractor progressing certain work on the vessels either incorrectly or out of sequence purely in order to trigger payments against the contract”.
Public Audit Committee
Meeting date: 16 June 2022
Colin Beattie
—and percentage of fabrication, that takes us back full circle to the value that was in the yard, which I believe, although I am talking from memory here, so this is open to correction, was something over £8 million, yet £128 million—