Skip to main content
Loading…

Seòmar agus comataidhean

Official Report: search what was said in Parliament

The Official Report is a written record of public meetings of the Parliament and committees.  

Criathragan Hide all filters

Dates of parliamentary sessions
  1. Session 1: 12 May 1999 to 31 March 2003
  2. Session 2: 7 May 2003 to 2 April 2007
  3. Session 3: 9 May 2007 to 22 March 2011
  4. Session 4: 11 May 2011 to 23 March 2016
  5. Session 5: 12 May 2016 to 4 May 2021
  6. Current session: 13 May 2021 to 18 September 2025
Select which types of business to include


Select level of detail in results

Displaying 1203 contributions

|

Public Audit Committee

Section 23 Report: “New vessels for the Clyde and Hebrides: Arrangements to deliver vessels 801 and 802”

Meeting date: 30 June 2022

Sharon Dowey

You disagree with that.

Public Audit Committee

Section 23 Report: “New vessels for the Clyde and Hebrides: Arrangements to deliver vessels 801 and 802”

Meeting date: 30 June 2022

Sharon Dowey

I might come back to more questions on that later on.

How fit for purpose is the current ferry procurement process in Scotland, and how does it compare with processes in other countries? That question is based on previous evidence that we have had. We are now procuring ferries from Turkey, but the ferries that we have procured are double the price that Norway is paying.

Public Audit Committee

Section 23 Report: “New vessels for the Clyde and Hebrides: Arrangements to deliver vessels 801 and 802”

Meeting date: 30 June 2022

Sharon Dowey

Section 6.9 of your submission states:

“CMAL were told that they should not seek a Ministerial direction by the Ministers in relation to contract award of the Vessels to FMEL. However, the Board were sufficiently concerned about the Contracts in all the circumstances instead to seek a letter from the Ministers holding CMAL harmless in the event that the Contracts encountered the financial and technical issues identified in the risks paper.”

At that point, you seemed very, very concerned. I still do not understand why CMAL did not just go in and cancel the contract.

Public Audit Committee

Section 23 Report: “New vessels for the Clyde and Hebrides: Arrangements to deliver vessels 801 and 802”

Meeting date: 30 June 2022

Sharon Dowey

Therefore, you were told to go in—

Public Audit Committee

Section 23 Report: “New vessels for the Clyde and Hebrides: Arrangements to deliver vessels 801 and 802”

Meeting date: 30 June 2022

Sharon Dowey

I have a question about the ports. The two ferries that are coming into service run on diesel and liquefied natural gas. Has work started on the bunkering facilities to store that? It has also been commented on that the vessels are larger than the ones that are currently in operation, so the ports are too short to take them. Again, has work started in that regard?

Public Audit Committee

Section 23 Report: “New vessels for the Clyde and Hebrides: Arrangements to deliver vessels 801 and 802”

Meeting date: 30 June 2022

Sharon Dowey

Are they expected to be completed by the time the vessels come into operation?

Public Audit Committee

Section 23 Report: “New vessels for the Clyde and Hebrides: Arrangements to deliver vessels 801 and 802”

Meeting date: 30 June 2022

Sharon Dowey

Section 3 of your submission is on “Provision of Refund Guarantees”. In section 3.6, you state that

“CMAL had no awareness of, or involvement in, these exchanges.”

That was in reference to exchanges between MSPs and so on about the non-provision of the refund guarantee from Ferguson Marine Engineering Ltd. When did you find out that FMEL was not giving the builders refund guarantee and why did you not go back to the tendering process at that point?

Public Audit Committee

Section 23 Report: “New vessels for the Clyde and Hebrides: Arrangements to deliver vessels 801 and 802”

Meeting date: 30 June 2022

Sharon Dowey

Good morning. On procurement, which you mentioned in your opening statement, one of the stated aims on your website is to be cost effective. To what extent do you consider the procurement of vessels 801 and 802 to be cost effective?

Public Audit Committee

Section 23 Report: “New vessels for the Clyde and Hebrides: Arrangements to deliver vessels 801 and 802”

Meeting date: 30 June 2022

Sharon Dowey

What minister was it?

Public Audit Committee

Section 23 Report: “New vessels for the Clyde and Hebrides: Arrangements to deliver vessels 801 and 802”

Meeting date: 30 June 2022

Sharon Dowey

Why did you not get a copy of that? It says in the paperwork somewhere that you asked for a letter of comfort. You state:

“The chair requested that Transport Scotland provide CMAL with a letter of comfort if required. John Nicholls agreed that a letter of comfort would be provided to CMAL.”

However, there does not seem to be a lot of communication or evidence to show that the letter of comfort was put in.